Ask three contractors to price a building from a set of plans and you will often get three very different numbers. Usually none of them is dishonest. Each has made different assumptions about quantities, materials and what is included. A bill of quantities, or BOQ, removes those assumptions.
What a BOQ is
A BOQ breaks the building into measured items — excavation in cubic metres, concrete by grade, steel in kilograms, brickwork, plaster, flooring and paint in square metres, doors and windows by count — each with a clear description. Contractors then price the same list, so their quotes can be compared line by line.
What a good BOQ includes
- Quantities taken from the drawings, not estimated from the built-up area.
- Specifications for each item — concrete grade, steel grade, brick type, tile size and finish.
- Named brands or approved equivalents for cement, steel, pipes, wires, fittings and waterproofing.
- Every trade: civil, plumbing, electrical, fire-fighting, finishes and external works.
- Provisional sums for items that cannot be fixed yet, shown separately so they don’t hide in the total.
Why “rate per square foot” isn’t enough
A per-square-foot price is useful for a first budget, but it hides everything that makes buildings differ: foundations on weak soil, a basement, a lift, the quality of finishes, the amount of glazing. A BOQ shows where the money goes, and makes changes easy to price later.
How we use it
Every EarthEdition design includes a BOQ prepared from the structural and services drawings. Clients use it to tender the work, to check bills during construction, and to decide where to spend more and where to save.
Have drawings but no BOQ? Send them to us and we can prepare one.